Question: Describe how the J b) What is the difference between qualitative and quantitative risk analy Question 2: The data identified below was listed in a
Describe how the J b) What is the difference between qualitative and quantitative risk analy Question 2: The data identified below was listed in a project's latest status report Budgeted cost work schedule $36,000 Budgeted cost of work performed $ 30,000 Actual cost of work performed $33,000 120,000 Original length of the project is 10 months. Using these data, calculate the following a. What is the value of CPI and SPI? b. What is the expected cost at completion? c. How much money will be needed from the time of the report tocomplete the project? d. What is the cost variance at completion? e. How is the project tracking? ts it ahead of schedule or behindschedule? ls it under budget or over budget