Question: Describe technical constrained scheduling and resource constrained scheduling and give at least three examples of each that are different than the book. Be sure to

Describe technical constrained scheduling and resource constrained scheduling and give at least three
examples of each that are different than the book. Be sure to read your Gido et al. book to
understand what these refer to.
Technical constrained scheduling: Technical constraints that relate to technical constrained
scheduling are not technical requirements requested by the customer; these are technical constraints
on the schedule!
Resource constrained scheduling: We are NOT asking you to illustrate how the resource constraints
(such as budget or lack of materials) prevent you from completing the project. We are asking you to
illustrate resource constrained scheduling impacts the scheduling of the predecessor and successor.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!