Question: Description of project Predecessor Activity A . B D E F G H . 1 J Activity time (days) 15 8 5 6 8 7

Description of project Predecessor Activity A . B

Description of project Predecessor Activity A . B D E F G H . 1 J Activity time (days) 15 8 5 6 8 7 4 2 3 3 2 A B D E, F F F HI JG Prepare a network diagram (use the AON format) and calculate the critical path(s), the early start and finish times, the late start and finish times and the total slack of each activity