Question: detail solution pls For the following precedence network: 9 5 2 2 4 6 8 8 7 2 S 3 5 7 End 6 10

detail solution pls

detail solution pls For the following precedence network: 9 5 2 2

For the following precedence network: 9 5 2 2 4 6 8 8 7 2 S 3 5 7 End 6 10 6 4 5 13 10 12 a) Compute the earliest start time, earliest finish time, latest finish time, latest start time, and activity slack time. b) Identify the critical activities. c) Determine the duration of the project