Question: Determine question 2 8 to 3 1 based on the following problem: Consider the project with the following estimates for activity times and precedence relationships:

Determine question 28 to 31 based on the following problem:
Consider the project with the following estimates for activity times and precedence relationships:
\table[[Activity,\table[[Optimistic],[Time]],\table[[Most],[Likely Time]],\table[[Pessimistic],[Time]],\table[[Immediate],[Predecessor(s)]]],[A,3,4,5,-.],[B,5,7,9,-.],[C,2,3,10,A],[D,2,5,8,B],[E,1,7,7,B],[F,3,5,7,C, D],[G,7,8,9,D, E],[H,2,6,10,F]]
 Determine question 28 to 31 based on the following problem: Consider