Question: Determine the critical path and project completion time. Select the critical path ( s ) below. ( Mark all that apply. ) a . B
Determine the critical path and project completion time. Select the critical paths below. Mark all that apply.
a BEFIK
b BDGHJK
c BEFIK
d BCGHJK
Activity Activity Time days Immediate Predecessors
A
B
C A B
D A B
E A B
F C E
G C D
H G
I F G
J E H
K I, J