Question: Determine the ES, EF, LS, LF and slack for each activity. You are given the project network/precedence diagram and activity times (in weeks) shown below.
Determine the ES, EF, LS, LF and slack for each activity.
You are given the project network/precedence diagram and activity times (in weeks) shown below. (18) (12) Start B (7) Finish (30) C(4) (20) (b) Determine the ES, EF, LS, LF, & slack for each activity. Indicate which activities are on the critical path On Critical Path? Indicate with a (LS-ES) or (LF-EF) Slack Activity Time ES EF LS LF Activity A B C D E F