Question: Determine the ES, EF, LS, LF and slack for each activity. You are given the project network/precedence diagram and activity times (in weeks) shown below.

Determine the ES, EF, LS, LF and slack for each activity.
Determine the ES, EF, LS, LF and slack for each
Determine the ES, EF, LS, LF and slack for each
You are given the project network/precedence diagram and activity times (in weeks) shown below. (18) (12) Start B (7) Finish (30) C(4) (20) (b) Determine the ES, EF, LS, LF, & slack for each activity. Indicate which activities are on the critical path On Critical Path? Indicate with a (LS-ES) or (LF-EF) Slack Activity Time ES EF LS LF Activity A B C D E F