Question: Determine the following table( three activity time estimators) NOTE: assume preceding yourself Activity Designation Time estimators (weeks) a m b 1.Design A 10 22 28
Determine the following table( three activity time estimators)
NOTE: assume preceding yourself
| Activity | Designation | Time estimators (weeks) a m b | ||
| 1.Design | A | 10 | 22 | 28 |
| 2.Build prototype | B | 1 | 4 | 7 |
| 3.Evaluate equipment | C | 4 | 6 | 14 |
| 4.Test prototype | D | 1 | 2 | 3 |
| 5.Write report | E | 1 | 5 | 9 |
| 6.Write method report | F | 7 | 8 | 9 |
| 7.Write final report | G | 2 | 2 | 2 |
Calculate the following
.Expected time (ET)
.Activity variance 2
.Critical path
.Identify all paths in network and their estimated completion times and variances
.Determine the probability of completing the project in desired weeks(39 weeks) ....using normal probability distribution