Question: Determine the following table( three activity time estimators) NOTE: assume preceding yourself Activity Designation Time estimators (weeks) a m b 1.Design A 10 22 28

Determine the following table( three activity time estimators)

NOTE: assume preceding yourself

Activity

Designation

Time estimators (weeks)

a m b

1.Design

A

10

22

28

2.Build prototype

B

1

4

7

3.Evaluate equipment

C

4

6

14

4.Test prototype

D

1

2

3

5.Write report

E

1

5

9

6.Write method report

F

7

8

9

7.Write final report

G

2

2

2

Calculate the following

.Expected time (ET)

.Activity variance 2

.Critical path

.Identify all paths in network and their estimated completion times and variances

.Determine the probability of completing the project in desired weeks(39 weeks) ....using normal probability distribution

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!