Question: Determine the least-cost schedule for the network constructed in Question 28 using simple compression. Show the logical steps in the compression table provided below with
Determine the least-cost schedule for the network constructed in Question 28 using simple compression. Show the logical steps in the compression table provided below with precedence network diagrams to reduce
Overhead costs = $300/day

Activity A B D Normal Duration 6 15 12 11 Crash Duration 4 5 6 3 Normal Cost ($) 1,500 4,000 3,400 4,000 Crash Cost ($) 1,700 4,500 4,000 5,200 Compression / Crashing Activity A Duration Slope 1 N 3 4 5 6 7 A B D Days Cut Project Duration Additional Cost/Day Direct Cost Overhead Cost Total Cost Activity A B D Normal Duration 6 15 12 11 Crash Duration 4 5 6 3 Normal Cost ($) 1,500 4,000 3,400 4,000 Crash Cost ($) 1,700 4,500 4,000 5,200 Compression / Crashing Activity A Duration Slope 1 N 3 4 5 6 7 A B D Days Cut Project Duration Additional Cost/Day Direct Cost Overhead Cost Total Cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
