Question: . Determine the logical steps to reduce SEVEN (7) days of the following project $100/day. with the least amount of cost increasing. The indirect (overhead)

 . Determine the logical steps to reduce SEVEN (7) days ofthe following project $100/day. with the least amount of cost increasing. Theindirect (overhead) costs are D Lag: FS + 2 B G AE F H Lag: FS + 3 C Activity ES Duration EFLS TF FF LF Determine the logical steps to reduce SEVEN (7)days of the following project with the least amount of cost increasing.The indirect (overhead) costs are $100/day. Activit Time Time Cost Cost TimeCost Slope yID Normal Crash Normal Crash Difference | Difference ($/Day) A- 4 4 $100 $100 B | A 7 | 5 $200| $110 Cc A 10 10 $300 $300 D B 7 2$500 | $300 | E B (FS +3) 4 2 $100 $50F E 3 | 1 $150 | $50 | G | D(FS+2),F7 | 4 $280 $100 | H | C,G 7 5 $500| $300 . Cycle #0. Activity to Can Be Days Cost perCost for Direct Project Indirect Total Cost Cycle # Shorten Shortened ShortenedDay Cycle Cost Duration Cost O W N 5 6Activity Time TimeSlope . Cycle #1. Reduce Activity ( days) ID Normal Crash ($/Day)

A 4 4 B 7 5 C 10 10 D 7 2E 4 2 F 3 D Lag: FS + 2 G AH 7 5 B G A E F H Lag: FS +3 C Activity ES Duration EF LS TF FF LF. Cycle #1.Reduce Activity days) Activity to Can Be Days Cost per Cost forDirect Project Indirect Cycle # Total Cost Shorten Shortened Shortened Day CycleCost Duration Cost YOUAWN-OActivity Time Time Slope . Cycle #2. Reduce Activity( days) ID Normal Crash ($/Day) A 4 4 B 7 5C 10 10 D 7 2 E 4 2 F 3 DLag: FS + 2 G 4 H 7 5 B G AE F H Lag: FS + 3 C Activity ES Duration EFLS TF FF LF. Cycle #2. Reduce Activity ( days) Activity toCan Be Days Cost per Cost for Direct Project Indirect Cycle #Total Cost Shorten Shortened Shortened Day Cycle Cost Duration Cost O YOUAWNCycle #3. Reduce Activity ( #_H, Lag: FS+3 C iFF days) ActivityTime Time Slope ID Normal Crash ($/Day) A | 4 4 B' 7 5 c | 10 10 D | 7 2 E

. Determine the logical steps to reduce SEVEN (7) days of the following project $100/day. with the least amount of cost increasing. The indirect (overhead) costs are D Lag: FS + 2 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF Determine the logical steps to reduce SEVEN (7) days of the following project with the least amount of cost increasing. The indirect (overhead) costs are $100/day. Activit Time Time Cost Cost Time Cost Slope yID Normal Crash Normal Crash Difference | Difference ($/Day) A - 4 4 $100 $100 B | A 7 | 5 $200 | $110 Cc A 10 10 $300 $300 D B 7 2 $500 | $300 | E B (FS +3) 4 2 $100 $50 F E 3 | 1 $150 | $50 | G | D(FS+2),F 7 | 4 $280 $100 | H | C,G 7 5 $500 | $300 . Cycle #0. Activity to Can Be Days Cost per Cost for Direct Project Indirect Total Cost Cycle # Shorten Shortened Shortened Day Cycle Cost Duration Cost O W N 5 6Activity Time Time Slope . Cycle #1. Reduce Activity ( days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F 3 D Lag: FS + 2 G A H 7 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF. Cycle #1. Reduce Activity days) Activity to Can Be Days Cost per Cost for Direct Project Indirect Cycle # Total Cost Shorten Shortened Shortened Day Cycle Cost Duration Cost YOUAWN-OActivity Time Time Slope . Cycle #2. Reduce Activity ( days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F 3 D Lag: FS + 2 G 4 H 7 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF. Cycle #2. Reduce Activity ( days) Activity to Can Be Days Cost per Cost for Direct Project Indirect Cycle # Total Cost Shorten Shortened Shortened Day Cycle Cost Duration Cost O YOUAWN Cycle #3. Reduce Activity ( #_H, Lag: FS+3 C iFF days) Activity Time Time Slope ID Normal Crash ($/Day) A | 4 4 B ' 7 5 c | 10 10 D | 7 2 E | 4 2 F | 3 1 e | 7 4 Ho| 7 5 G H Activity Duration Cycle #3. Reduce Activity ( days) Activity to| Can Be Days Cost per| Cost for Direct Project Indirect Cycle# | chorten | Shortened | Shortened Day Cycle Cost Duration Cost Total Cost N ON - Activity Time Time Slope . Cycle #4. Reduce Activity ( days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F 3 D Lag: FS + 2 G 7 4 H 7 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF Cycle #4. Reduce Activity ___ ( days) Activity to Shorten Cycle # Can Be Shortened Days Shortened | Cost per Day Cost for Cycle Direct Cost Project Indirect Duration = Cost | Total Cost Nooa b~ N = . Cycle #5. Reduce Activity Activity Time Time Slope days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F D 3 Lag: FS + 2 A H 7 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF Cycle #5. Reduce Activity ( days) Activity to| Can Be Days Cost per| Cost for Direct Project Indirect Cycle # Shorten | Shortened | Shortened Day Cycle Cost Duration = Cost Total Cost 0 N A WON = Activity Time Time Slope . Cycle #6. Reduce Activity days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F 3 D Lag: FS + 2 G 7 4 H 7 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF Cycle #6. Reduce Activity ___ ( Activity to | Shorten | Shortened | Shortened days) Cost per Day Cost for Cycle Direct Cost Project Duration Indirect Cost Total Cost N O A WON - Activity Time Time Slope . Cycle #7. Reduce Activity ( days) ID Normal Crash ($/Day) A 4 4 B 7 5 C 10 10 D 7 2 E 4 2 F 3 D Lag: FS + 2 G 4 H 5 B G A E F H Lag: FS + 3 C Activity ES Duration EF LS TF FF LF. Cycle #7. Reduce Activity days) Activity to Can Be Days Cost per Cost for Direct Project Indirect Cycle # Total Cost Shorten Shortened Shortened Day Cycle Cost Duration Cost O 2 3 YOU A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!