Question: Determine the net present value for a project that costs $253,494 and is expected to yield cash flows of $29,000 per year for the first

Determine the net present value for a project that costs $253,494 and is expected to yield cash flows of $29,000 per year for the first ten years, $37,000 per year for the next ten years, and $50,000 per year for the following ten years. Your firm's cost of capital is 12.00%. Solve for NPV using a cash flow schedule.

I need the cash flow schedule Please!