Question: Determine the sequence and makespan for the following 3-machine flow shop problem to minimize the makespan. Is the sequence optimal? (Hint: Consider if the
Determine the sequence and makespan for the following 3-machine flow shop problem to minimize the makespan. Is the sequence optimal? (Hint: Consider if the problem is a special problem first, such as second machine is dominated.) Job Pi (minutes) P2 (minutes) P3 (minutes) J 9 7 11 J2 12 11 14 J3 11 6 16 J4 14 13 15 J5 8 5 9 J6 13 12 15 J 966 8
Step by Step Solution
There are 3 Steps involved in it
The sequence for this 3machine flow shop problem is J4J6J5J3J2J7J1 with a makespan of 48 minute To d... View full answer