Question: Determine the work content (standard time) for the union assembly by dividing it into 3 elements as follows: A. pick up of nut and pipe

Determine the work content (standard time) for the union assembly by dividing it into 3 elements as follows: A. pick up of nut and pipe parts from bins, dipping of both parts in lubricants. Break point : Start of reaching for both nut and pipe.

B. Threading together of the nut and pipe parts till tightened. Break point: Start if threading motion.

C Inspection Both ends of union, and drop off. Break point: Start of Inspection.

Use an average standard performance for three complete cycles and a 10% allowance across all elements. Average rating for each of the elements average 3 complete cycle is assumed at standard performance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!