Question: Determine True / False ( No Explanations needed ) : ( i ) The CPM method was developed primarily for the construction industry. ( ii
Determine TrueFalse No Explanations needed:
i The CPM method was developed primarily for the construction industry.
ii CPM uses a fixed value for project duration.
iii A Dummy Activity may sometimes have nonzero duration.
iv In a CPM arrow network, when two or more arrows begin at the same node, this means
that the work must end at the same time.
v The Forward & Backward Pass algorithms calculate EST and LST respectively, of
all activities.
vi The Critical Path time is defined as the longest possible path of the network.
vii Backward Pass algorithm assumes the duration of the project as obtained by the
Forward Pass.
viii On the ActivityonArrow network, the nodes represent a point in time.
ix To draw an ActivityonArrow network, Activities IPA are needed.
x Calculation of Duration of a Project using Average Productivity is usually an
optimistic one.
xi Cashflow Analysis using CPM can be done by EST or LST Schedule
xii Resource Leveling using CPM is usually a trialanderror method
xiii For a PERT model if each activity has a then effectively it becomes a CPM
model.
xiv The Expected Time for PERT is a weighted average of three times
xv In the Monte Carlo Simulation Method, Activity Durations are generated by random
numbers.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
