Question: Determine which project is better using A) Benefit to cost ratio only B) Using a benefit to cost ratio on incremental investment (adjusting to be
Determine which project is better using A) Benefit to cost ratio only B) Using a benefit to cost ratio on incremental investment (adjusting to be compatible with Present Worth method): Projects A1 A2 ?? A4 PW of Benefits (B) PW of Costs (I+C-C) 180 123 10 91 126 74 36 32