Question: Determining Costs, Budget, and Earned Value Assignment (Chapter 7) For all 3 cases determine the following: CPI . Cost Variance FCAC= TBC/CPI FCAC-CAC+ (TBC-CEV) .
Determining Costs, Budget, and Earned Value Assignment (Chapter 7) For all 3 cases determine the following: CPI . Cost Variance FCAC= TBC/CPI FCAC-CAC+ (TBC-CEV) . TCPI = (TBC-CEV) / (TBC-CAC) TCPI Case 1 Total Budgeted Cost- Cumulative Budgeted Cost- Cumulative Actual Cost- Cumulative Earned Value= S120,000 $85,000 $95,000 $81,000 Case 2 Total Budgeted Cost- Cumulative Budgeted Cost- Cumulative Actual Cost Cumulative Earned Value- $145,000 S68,000 $72,000 S69,000 Case 3 Total Budgeted Cost- Cumulative Budgeted Cost- Cumulative Actual Cost- Cumulative Earned Value- $100,000 $60,000 $58,000 $61,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
