Question: deture-up Pine Village needs some additional recreation fields. Construction will cost $300,000, and annual O&M expenses are $85,000. The city council estimates that the value
deture-up Pine Village needs some additional recreation fields. Construction will cost $300,000, and annual O&M expenses are $85,000. The city council estimates that the value of added youth leagues is about $200,000 annually. In year 6 another $75,000 will be needed to refurbish the fields. The salvage value is estimated to be $50,000 after 10 years. Draw the cash flow diagram. 2-77
Step by Step Solution
There are 3 Steps involved in it