Question: Develop a EOQ solution and calculate total relevant costs for the gross requirements in the following table* Holding cost =$250/ unit week setup cost =$200,

Develop a EOQ solution and calculate total relevant costs for the gross requirements in the following table* Holding cost =$250/ unit week setup cost =$200, lead time =1 week, beginning irventory =40 What is the average demand per week? (onter your cosponses wth 2 decimal places) Calculate Economic Order Quantify (EOQ) (enter your rosponses ast whole numbers) Calculate the number of periods for POQ (enter your responses as whole numbers) Develop a POQ solution (enter your responses as whole numbers) Setup cost for 12 weeks is $ (enter your response as a whole number). Carrying cost for 12 weeks is 5 (enter your response as a whole number). The total cost is $ (enter your response as a whole number)