Question: Develop a Gantt Chart and identify resource conflicts: Fill out the boxes and create a bar chart Calculate how many compressors are needed per day.

 Develop a Gantt Chart and identify resource conflicts: Fill out the

Develop a Gantt Chart and identify resource conflicts: Fill out the boxes and create a bar chart Calculate how many compressors are needed per day. The company has 6 compressors available. On which days do resource conflicts occur? Activity Duration Compressors 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 (Days) Needed Total compressors needed per day Apply resource leveling and resolve the resource conflicts. What is the duration of the project