Question: Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table. a Period 123456789101112 Gross requirements 20 30 30

Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table". a Period 123456789101112 Gross requirements 20 30 30 70 30 20 70 50 *Holding cost = $2.50lunit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40. Develop a lot-forlot solution (enter your responses as whole numbers). Gross requirements On-hand at beginning of period On-hand at end of period Order receipt Order release