Question: Develop a minimum makespan schedule using Johnson's rule. Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is Is there any


Develop a minimum makespan schedule using Johnson's rule. Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is Is there any idle time on either machine? Round your answers to the nearest whole number. If there is no an idle time on a machine, enter zero. Mill:Drill:hour(s)hour(s) Check My Work (1 remaining) Develop a minimum makespan schedule using Johnson's rule. Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is Is there any idle time on either machine? Round your answers to the nearest whole number. If there is no an idle time on a machine, enter zero. Mill:Drill:hour(s)hour(s) Check My Work (1 remaining)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
