Question: Develop a model in MS project. Also, enter the total project duration. Refer to the following table for information on a project: Duration Activities B

Develop a model in MS project. Also, enter the total project duration.
Refer to the following table for information on a project: Duration Activities B D E F F G WN ANNAN Predecessor Resources 2 A(SS+3) 2 A 2 | B(FF+3),C 2 D(SS+2),D(FF+3) 2 D(SS+3),D(FF+4) 1 E 2 F G 2Step by Step Solution