Question: Develop a MRP table to identify the planned order release using lot - for - lot replenishment. b . Revise the MRP table using a

Develop a MRP table to identify the planned order release using lot-for-lot replenishment.
b. Revise the MRP table using a fixed order quantity of 80 units.
c. Due to unreliable supply, we now want to maintain a one-week safety lead time in addition to the 2 weeks
of suppliers lead time. If we use lot-for-lot replenishment policy, would there be a problem? As a
production planner, how would you report a change notice or exception notice?
(a) Rules: Lot-for-Lot; Lead Time =2 weeks
Week 12345678910
Demand 41648442848627184930
Scheduled Receipt 2020
On-hand: 120
Net Demand
Planned Order Receipts
Planned Order Release
Report:
(b) Rules: Fixed Order Quantity =80 or Multiples of 80; Lead Time =2 weeks
Week 12345678910
Demand 41648442848627184930
Scheduled Receipt 2020
On-hand: 120
Net Demand
Planned Order Receipts
Planned Order Release
Report:
(c) Rules: Lot-for-Lot; Lead Time =2 weeks; Safety Lead Time =1 week
Week 12345678910
Demand 41648442848627184930
Scheduled Receipt 2020
On-hand: 120
Net Demand
Planned Order Receipts
Planned Order Release
Report:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!