Question: Develop a own cost estimate of your project, for each activity (a minimum of 10): provide: The type and quantity of each resource on each

Develop a own cost estimate of your project, for each activity (a minimum of 10):

provide:

  • The type and quantity of each resource on each activity (e.g., how many hours of labor, materials, etc.).
  • The cost for each unit (e.g., how much does each hour or materials cost).
  • Make sure that you show the total cost for each activity.
  • Make sure you show the total cost of the project, which is the sum of all activity costs.
  • One example of how to calculate the cost estimate for each activity is: activity days, multiplied by man-hours per day, multiplied by the cost per hour.
  • Your cost estimate should be produced in Excel and then uploaded as either an excel file or PDF.

Use Activities listed below to answer the questions listed above!

Activity ID Activity Description Duration (Days) Predecessors
1 Project Kick-off 1 -
2 Gather User Requirements 5 2
3 Gather User Requirements 5 2
4 Conduct Market Research 7 2
5 Crete Wireframes 7 3, 4
6 Review Wireframes with Stakeholders 3 5
7 Finalize App Design 5 6
8 App Development Begins 3 7
9 Set Up Development Environment 2 8
10 Development User Interface 10 8
11 Implement Booking System Integration 7 8
12 Create Instructional Content 8 8
13 Implement User Tracking 5 8
14 Conduct User Acceptance Testing 5 10,11,12,13
15 Address Bugs and Issues 5 14
16 Conduct Beta Testing 15 15
!7 App Launch on IOS and Android 3 16
18 Promote App and User Acquisition 15 17
19 Evaluate User Engagement 10 18
20 Hand-Off Project 1 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!