Question: Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the

Develop a resource schedule in the loading chart that follows. Use the parallel
method and heuristics given. Be sure to update each period as the computer would
do. Note: activities 2,3,5, and 6 use two of the resource skills. Three of the resource
skills are available. How has slack changed for each activity? Has the risk of being
late changed? How?
348
00
358
1
135
33
448
2
365
22
583
2
11
1
1
23
3
8610
2
2
8
0
10
0
List the order in which your
activities are scheduled
/_____/_____/_____/
/_____/_____/_____/
2
0
00
33
0
22
23
Use the following heuristics:
Minimum slack
Smallest duration
Lowest identification number
ID
LS DUR
SL
LF
ES EF
Legend
SL
DUR ES LF SL
What is the schedule slack for 1____,3____, and 4_____?
Which activities are critical now? _____________________
ID RES 012345678910111213
1103
2303
3418
4538
53
62
Resources scheduled
Resources available 3333333333333
1
2
2
1
2
2
RES
6.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!