Question: Develop a solution for the following line balancing problem, allowing a theoretical cycle time of 300 seconds. Work Task Task Time (seconds) Task Predecessor(s) A
- Develop a solution for the following line balancing problem, allowing a theoretical cycle time of 300 seconds.
| Work Task | Task Time (seconds) | Task Predecessor(s) |
| A | 70 | - |
| B | 60 | A |
| C | 120 | B |
| D | 60 | - |
| E | 240 | C, D |
| F | 100 | A |
| G | 190 | E, F |
- Draw a network diagram of precedence relationships.
- Compute the theoretical minimum number of workstations.
- Balance this line.
- What is the actual cycle time?
- What is the efficiency of the line obtained in part d?