Question: Develop a solution for the following line balancing problem. Work Task Task Time (seconds) Task Predecessor(s) A 70 -- B 160 A C 190 B

Develop a solution for the following line balancing problem.

Work Task

Task Time (seconds)

Task Predecessor(s)

A

70

--

B

160

A

C

190

B

D

60

--

E

170

C, D

F

100

B, D

G

190

E, F

  1. Draw the precedence diagram for the set of tasks.

  1. Calculate the theoretical minimum number of workstations.

  1. What tasks are assigned to which stations?

  1. Does the solution have the minimum number of stations? Explain.

  1. How much idle time is there, summed over all workstations?

  1. What is the efficiency of this line?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!