Question: Develop a spreadsheet for Earliest Due Date (EDD) the five-job example Job Process Time (days) Due date (days) D 2 4 C 5 6 A
Develop a spreadsheet for Earliest Due Date (EDD) the five-job example
Job Process Time (days) Due date (days)
D 2 4
C 5 6
A 7 8
B 1 12
E 6 18
Compute, for each job :
a. Start time
b. Completion (or End) time
c. Flow time
d. Lateness
e.Tardiness
Compute aggregate performance of the EDD rule :
a. Lateness: Average, Maximum
b. Tardiness: Average, Maximum
c. Service level and utilization
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts