Question: Develop a status report for the project at the end of period 8 given that at the end of this period, activities A, B, C,
Develop a status report for the project at the end of period 8 given that at the end of this period, activities A, B, C, D, E are 100; 100; 100; 25%; and 33% complete respectively. Activity F has not started at this stage. The actual costs for incurred for these activities are R300; R2200; R1500; R300; 300. What information are you prepared to tell the customer about the status of the project at the end of period 8?