Question: Develop a work breakdown structure ( WBS ) for the information in the photo.Part 1 Project Description The new computer - controlled conveyor belt is

Develop a work breakdown structure (WBS) for the information in the photo.Part 1
Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within 1 millimeter. The project will produce a new system for future installations, and for
replacement of those in the field, at a low cost. The computer-controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to
update with future technologies.
The Project Priority Matrix for the Conveyor Belt Project (CBP) is:
Table A2.9 has been developed for you to use in completing the project exercises.
TABLE A2.9
Conveyor Belt Project; WBS
Conveyor Belt Project
Hardware
Operating system
Utilities
System integration
Hardware specifications
Hardware design
Hardware documentation
Prototypes
Order circuit boards
Assemble preproduction models
Kernel specifications
Drivers
Disk drivers
Serial I/O drivers
Memory management
Operating system documentation
Network interface
Utilities specifications
Routine utilities
Complex utilities
Utilities documentation
Shell
Architectural decisions
Integration first phase
System hard/software test
Project documentation
Integration acceptance testing
Assignment
Develop the WBS outline using the software available to you.
Question
Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?
 Develop a work breakdown structure (WBS) for the information in the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!