Question: Develop an estimated duration for each activity. Using a project start time of 0 (or May 15) and a required project completion time of 180
-
Develop an estimated duration for each activity.
-
Using a project start time of 0 (or May 15) and a required project completion time of 180 days (or November 15), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an acceptable baseline schedule for completing the project within 180 days (or by November 15). Describe the revisions you made.
-
Determine the critical path, and identify the activities that make up the critical path.
-
Produce a bar chart (Gantt chart) based on the ES and EF times from the schedule in item 2.