Question: Develop material requirement plan. The solution should be filled in the blank form (if your choice is zero, please do not fill it in the

 Develop material requirement plan. The solution should be filled in the
Develop material requirement plan. The solution should be filled in the blank form (if your choice is zero, please do not fill it in the form and just let blank).
Please make CLEAR your MPS and product. All materials use lot-for-lot policy.
Abbr:
GR=Gross requirements
POH=Projected on hand inventory
NR=Net requirement,
RT=Planned order receipts,
RS=Planned order releases,
LT=Lead Time;
All information are in, cannot add anything so ,Please I need show the process step by step , I need answers as soon as possible thank u lot.
*Problem 1: Suppose Southern Mechanics has different forecast as follows:
blank form (if your choice is zero, please do not fill it
The current cost composition is as follows:
Output Regular time = $2 per skateboard
Overtime = $3 per skateboard Subcontract = $6 per skateboard
Inventory = $1 per skateboard per month on average inventory
Back orders = $5 per skateboard per month
Southern Mechanics has capacity of outputing 300 skateboards per month.
And the over time capacity is 80 and subcontracting capacity is 90.
The initial inventory is zero and should have an ending inventory of zero in the last month. (if your choice is zero, please do not fill it in the form and just left blank)
-> Please develop aggregate plan
Problem2: MRP Southern Mechanics may make different master production schedules:
in the form and just let blank). Please make CLEAR your MPS
Develop material requirement plan.
The solution should be filled in the blank form (if your choice is zero, please do not fill it in the form and just let blank).
Please make CLEAR your MPS and product. All materials use lot-for-lot policy.
Abbr: GR=Gross requirements
POH=Projected on hand inventory
NR=Net requirement,
RT=Planned order receipts
RS=Planned order release
LT=Lead time.
*Please answers are needed as soon as possible , Thank u!

Yoblem 1: suppose Southern Mechanics las diferent demand for as follows Forecast 1 2 3 4 5 6 Total 14 |150|200|350|400/500|200|1,800 The current cost composition is as follows: Output Regular time=S2 per skateboard Overtime - $3 per skateboard Subcontract - $6 per skateboard Inventory = Si per skateboard per month on average inventory Back orders = $5 per skateboard per month Southern Mechanics has capacity of outputing 300 skateboards per month. And the over time capacity is 80 and subcontracting capacity is 90. The initial inventory is zero and should have an ending inventory of zero in the last month. When solving every subproblem, please use the conditions described above and in the subproblem. Do not use conditions described in other subproblems. All solutions for the subproblems should be filled in the blank form given in Solution section (if your choice is zero, please do not fill it in the form and just left blank): e developegate plan Problem2: MRP Southern Mechanics may make different master production schedules: MPS 4 Agth week | 400 12" week 400 Forecast 1 2 3 4 5 6 Total 14 |150|200|350|400 500/200|1,800| MPS 4. Al 8th week | 400 12th weekl 400 Yoblem 1: suppose Southern Mechanics las diferent demand for as follows Forecast 1 2 3 4 5 6 Total 14 |150|200|350|400/500|200|1,800 The current cost composition is as follows: Output Regular time=S2 per skateboard Overtime - $3 per skateboard Subcontract - $6 per skateboard Inventory = Si per skateboard per month on average inventory Back orders = $5 per skateboard per month Southern Mechanics has capacity of outputing 300 skateboards per month. And the over time capacity is 80 and subcontracting capacity is 90. The initial inventory is zero and should have an ending inventory of zero in the last month. When solving every subproblem, please use the conditions described above and in the subproblem. Do not use conditions described in other subproblems. All solutions for the subproblems should be filled in the blank form given in Solution section (if your choice is zero, please do not fill it in the form and just left blank): e developegate plan Problem2: MRP Southern Mechanics may make different master production schedules: MPS 4 Agth week | 400 12" week 400 Forecast 1 2 3 4 5 6 Total 14 |150|200|350|400 500/200|1,800| MPS 4. Al 8th week | 400 12th weekl 400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!