Question: Develop MRP for component E. Lead times for all items are two weeks. 120 units of A are needed at the start of week 10.

Develop MRP for component E. Lead times for all items are two weeks. 120 units of A are needed at the start of week 10. There are currently 30 ufits of C and 100 of E on hand, and 50 units of C are in production and will be completed by te start of week 3. Lot size is multiples of 100 for all items