Question: Develop MRP for component E. Lead times for all items are two weeks. 120 units of A are needed at the start of week 10.

 Develop MRP for component E. Lead times for all items are

Develop MRP for component E. Lead times for all items are two weeks. 120 units of A are needed at the start of week 10. There are currently 30 ufits of C and 100 of E on hand, and 50 units of C are in production and will be completed by te start of week 3. Lot size is multiples of 100 for all items