Question: Develop MRP matrix Product A is made according to the bill of materials diagram shown below; 200 units of A are needed in week 5;
Develop MRP matrix
Product A is made according to the bill of materials diagram shown below; 200 units of A are needed in week 5; 300 in week 8. Product A lead-time = 1 week. I B C E(4) D(3) E(2) The table below shows additional data for the items B, C, D, and E. B D E E Lot size L4L L4L 500 900 Lead-time 2 3 2 Beginning inventory 0 0 200 500 Scheduled receipts none none 500 week 2 none