Question: Develop MRP records for all items needed for item F in the following product structure for product H, using the information provided in the following
- Develop MRP records for all items needed for item F in the following product structure for product H, using the information provided in the following tables. The lead time to complete product H is one week. Master production schedule (MPS) calls for 170, 130, and 100 units of demand for period 4, 5, and 6.
*Planned order schedules must be the same or multiples of Q amount **minimum on hand (ending inventory) quantity to be observed FORMAT FOR ENTRIES: All quantities are INTEGER (120, for example). Enter 0 if you do not have quantity for any period. PROVIDE THE FOLLOWING SELECTED VALUES:Planning Data
Data Category
D
E
F
G
I
Lot size rule
Q= 15*
L4L
L4L
Q=300*
L4L
Lead time
2 weeks
1 week
1 week
2 weeks
2 weeks
Safety stock
15**
25
20
35
0
Scheduled receipts
None
none
1,300 (wk 1)
700 (wk 1)
900 (wk 1)
Beginning inventory
30
40
20
50
0
Planned Order Release Quantities for Product H
Period 1
Period 2
Period 3
Period 4
Period 5
Gross Requirements Quantities for Item F
Period 1
Period 2
Period 3
Period 4
Period 5