Question: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.
Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours. Make a comment.

\begin{tabular}{|c|c|c|c|} \hline \multirow{2}{*}{ Order } & TimeSinceOrderArrived & EstimatedMachine & Due Date \\ \cline { 2 - 4 } & (hours ago) & Time (hours) & (hours from now) \\ \hline 1 & 1 & 11 & 24 \\ \hline 2 & 3 & 8 & 22 \\ \hline 3 & 5 & 10 & 15 \\ \hline 4 & 6 & 8 & 10 \\ \hline 5 & 7 & 15 & 20 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts