Question: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.

Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours. Make a comment.

Develop separate schedules by using the FCFS and EDD rules. Compare the

\begin{tabular}{|c|c|c|c|} \hline \multirow{2}{*}{ Order } & TimeSinceOrderArrived & EstimatedMachine & Due Date \\ \cline { 2 - 4 } & (hours ago) & Time (hours) & (hours from now) \\ \hline 1 & 1 & 11 & 24 \\ \hline 2 & 3 & 8 & 22 \\ \hline 3 & 5 & 10 & 15 \\ \hline 4 & 6 & 8 & 10 \\ \hline 5 & 7 & 15 & 20 \\ \hline \end{tabular}