Question: Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and

Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and each component except B are one week. The lead time for B is three weeks. Sixty five units of A are needed at the start of week 8. There are currently 16 units of B and 110 units of E Projected on-hand, and 50 units of H are in production by a supplier and are scheduled to be received by the start of week 2.(Do not leave any empty spaces; input a 0 wherever it is required.)
Master Schedule
Week Beg. Inv. 12345678
Quantity 65
A LT =1 Beg. Inv. 12345678
Gross requirements
Scheduled receipts
Projected on-hand
Net requirements
Planned-order receipts
Planned-order releases
B(2) LT =3 Beg. Inv. 12345678
Gross requirements
Scheduled receipts
Projected on-hand
Net requirements
Planned-order receipts
Planned-order releases
C LT =1 Beg. Inv. 12345678
Gross requirements
Scheduled receipts
Projected on-hand
Net requirements
Planned-order receipts
Planned-order releases
E(2) E(4) LT =1 Beg. Inv. 12345678
Gross requirements
Scheduled receipts
Projected on-hand
Net requirements
Planned-order receipts
Planned-order releases
H(3) H(3) LT =1 Beg. Inv. 12345678
Gross requirements
Scheduled receipts
Projected on-hand
Net requirements
Planned-order receipts
Planned-order releases

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!