Question: Develop the network activity (AON) chart and identify the critical path for a project based on the table. Draw the activity network as a Gantt

Develop the network activity (AON) chart and identify the critical path for a project based on the table.

Draw the activity network as a Gantt chart using MSProject. What is the expected duration of the project?

Develop the network activity (AON) chart and

Activity Expected Duration Predecessors 5 Days B 10 Days A C 8 Days A D 1 Day A E 5 Days B,C F 10 Days DE G 14 Days F H 3 Days G 1 12 Days F J 6 Days H