Question: Develop the network activity chart and identify the critical path for a project based on the following information. Draw the activity network Activity Expected Duration

Develop the network activity chart and identify the critical path for a project based on the following information. Draw the activity network

Activity

Expected Duration

Predecessors

A

5 days

B

10 days

A

C

8 days

A

D

1 day

A

E

5 days

B, C

F

10 days

D, E

G

14 days

F

H

3 days

G

I

12 days

F

J

6 days

H, I