Question: Develop the network activity chart and identify the critical path for a project based on the following information. Draw the activity network Activity Expected Duration
Develop the network activity chart and identify the critical path for a project based on the following information. Draw the activity network
| Activity | Expected Duration | Predecessors |
| A | 5 days | |
| B | 10 days | A |
| C | 8 days | A |
| D | 1 day | A |
| E | 5 days | B, C |
| F | 10 days | D, E |
| G | 14 days | F |
| H | 3 days | G |
| I | 12 days | F |
| J | 6 days | H, I |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
