Question: develop the network (diagram with activity on node-examplw shown below) for planning and construction of the new hospital at arnold palmer. ACTIVITY SCHEDULED PRECEDENCE TIME

develop the network (diagram with activity on node-examplw shown below) for planning and construction of the new hospital at arnold palmer.

ACTIVITY SCHEDULED PRECEDENCE TIME ACTIVITY(IES) 1. Proposal and review 1 month 2. Establish master schedule 2 weeks 1 3. Architect selection process 5 weeks 1 4. Survey whole campus and its needs 1 month 1 5. Conceptual architect's plans 6 weeks 3 6. Cost estimating 2 months 2, 4,5 7. Deliver plans to board for consideration/decision 1 month 6 8. Surveys/regulatory review 6 weeks 6 9. Construction manager selection 9 weeks 6 10. State review of need for more hospital beds 3.5 months 7,8 ("Certificate of Need") 11. Design drawings 4 months 10 12. Construction documents 5 months 9, 11 13. Site preparation/demolish existing building 9 weeks 11 14. Construction start/building pad 2 months 12, 13 15. Relocate utilities 6 weeks 12 16. Deep foundations 2 months 14 17. Building structure in place 9 months 16 18. Exterior skin/roofing 4 months 17 19. Interior buildout 12 months 17 20. Building inspections 5 weeks 15, 19 91 Ornancy 1 month 20 Hospital (Pg 100 - 102). After reading the case, please respond to Discussion Questions 1 - 4 the network diagram with activity on node-example shown below for planning and construction of the new hospital at Amold Palmer. A BEGIN D E END F G 2. What is the critical path, and how long in
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock