Question: Developm (1. Consider the following data for a project to install a new server at the Northland Pines High School. Activity Activity Time (days) Immediate

Developm (1. Consider the following data for a

Developm (1. Consider the following data for a project to install a new server at the Northland Pines High School. Activity Activity Time (days) Immediate Predecessor(s) A 2 B 4. A 5 A D 2. B E B F 8 B, C G 3 D, E 5 F H 4 F - 7 G, H, I J a. Draw the network diagram. b. Calculate the critical path for this project. C. How much slack is in each of the activities G, H, and I? The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel. 2