Question: Differentiate the risk classifications in the table using red, yellow, and green shading using, red for high, yellow for medium, and green for low to

Differentiate the risk classifications in the table using red, yellow, and green shading using, red for high, yellow for medium, and green for low to produce a status report that immediately signals the severity of the impact without reading the details. Can you help me with a Risk visual for the following scenario?

The Quick Drop 100 transition team has met to identify project risks, explore contingency plans, and assign owners to watch for symptoms and address the risks. The team surfaced the following information:

  1. Julie is scheduled for a one week vacation during month three of the project.
  2. The supplier of a common set of hand tools for the manufacturing floor notified the Roto Air Purchasing department that the tools will not be available until one month after manufacturing is scheduled to start. Alternative suppliers are available.
  3. The Human Resources department has indicated that despite their best recruiting efforts the two openings for skilled welders have resulted in no qualified local applicants.
  4. The manufacturer of the custom-built rotor forming machine now expects to be one month past the last acceptable date for installing the machine. No other suppliers exist for this item.
  5. Roto Air uses a Just In Time (JIT) delivery system for major components used at the Florida plant. Hurricane season often interrupts or delays deliveries during one of the scheduled months of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!