Question: Dilemma BACKGROUND Sarah's project had now become more complex than she had anticipated. Sarah's company had a philosophy that the project manager would be assigned

Dilemma
BACKGROUND
Sarah's project had now become more complex than she had anticipated. Sarah's
company had a philosophy that the project manager would be assigned during
proposal preparation, assist in the preparation of the proposal, and take on the
role of the project manager after contract award, assuming the company would be
awarded the contract.
Usually, contract go-ahead would take place within a week or two after con-
tract award. That made project staffing relatively easy for most of the project man-
agers. It also allowed the company to include in the proposal a detailed schedule
based on resources that would be assigned upon contract award and go-ahead.
During proposal preparation, the functional managers would anticipate who
would be available for assignment to this project over the next few weeks. The
functional managers could then estimate with reasonable accuracy the duration
and effort required based on the grade level of the resources to be assigned. Since
the go-ahead date was usually within two weeks of contract award and the con-
tract award was usually within a week or so after proposal submittal, the schedule
that appeared in the proposal was usually the same schedule for the actual project
with very few changes. This entire process was based on the actual availability of
resources rather than the functional managers assuming unlimited resources and
using various estimating techniques.
Although this approach worked well on most projects, Sarah's new project
had a go-ahead date of three months after contract award. For the functional man-
agers, this created a problem estimating the effort and duration. Estimating now
had to be made based on the assumption of unlimited availability rather than the
availability of limited resources. Functional managers were unsure as to who
would be available three or four months from now, yet some type of schedule had
to appear in the proposal.
Sarah knew the risks. When the estimates were being prepared for her pro-
posal, the functional managers assumed that the average worker in the department
would be available and assigned to the project after go-ahead. The effort and dura-
tion estimates were then made based on the average employee. If, after go-ahead,
above-average employees would be assigned to Sarah's project, she could pos-
sibly see the schedule accelerated but had to make sure that cost overruns did not
happen because the fully loaded salary of the workers might be higher that what
was estimated in the proposal. If below-average workers are assigned, a schedule
slippage might occur, and Sarah would have to look at possible schedule compres-
sion techniques, hopefully without incurring added costs.
AWARD OF CONTRACT
Sarah's company was awarded the contract. Sarah had silently hoped that the
company would not get the contract, but it did. As expected, the go-ahead date
was three months from now. This created a problem for Sarah because she was
unsure as to when to begin the preparation of the detailed schedule. The functional
managers told her that they could not commit to an effort and duration based on
actual limited resource availability until somewhere around two to three weeks
prior to the actual go-ahead date. The resources were already spread thin across
several projects, and many of the projects were having trouble. Sarah was afraid
that the worst-case scenario would come true and that the actual completion date
would be longer than what was in the proposal. Sarah was certainly not happy
about explaining this to the client should it be necessary to do so.
 Dilemma BACKGROUND Sarah's project had now become more complex than she

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!