Question: Diners are served in a process with two resources. The first resource has a capacity of 0 . 9 diners per hour. The capacity of

Diners are served in a process with two resources. The first resource has a capacity of 0.9 diners per hour. The capacity of the second
resource is 1.1 diners per hour. The first resource has 1 worker and the second resource has 3 workers.
What is the labor content (in hours)?
Note: Do not round intermediate calculations. Round your answer to 2 decimal places.