Question: Dinners are prepared in a process with two resources. The first resource has a capacity of 4.6 dinners per hour. The capacity of the second

Dinners are prepared in a process with two resources. The first resource has a capacity of 4.6 dinners per hour. The capacity of the second resource is 6.3 dinners per hour. The first resource has 1 worker and the second resource has 10 workers. Demand for this process is 3.4 dinners per hour. Instruction: Round your answer to one decimal place. What is the average labor utilization (%) ? percent