Question: Dinners are prepared in a process with two resources. The first resource has a capacity of 11 dinners per hour. The capacity of the second

Dinners are prepared in a process with two resources. The first resource has a capacity of 11 dinners per hour. The capacity of the second resource is 13 dinners per hour. The first resource has 10 workers and the second resource has 8 workers. Demand for this process is 7.8 dinners per hour. Instruction: Round your answer to one decimal place. What is the average labor utilization (%) ? percent
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
