Question: Dinners are prepared in a process with two resources. The first resource has a capacity of 30 dinners per hour. The capacity of the second
Dinners are prepared in a process with two resources. The first resource has a capacity of 30 dinners per hour. The capacity of the second resource is 43 dinners per hour. The first resource has 10 workers and the second resource has 1 worker. Demand for this process is 38 dinners per hour.
*What is the average labor utilization??
Please solve this Q whit good explanation.