Question: Direct materials (2lb per bag, cost $3 per pound) Direct labor 1 hour per bag, cost $17 per hour) Static budget variable overhead $20000 Static
Direct materials (2lb per bag, cost $3 per pound)
Direct labor 1 hour per bag, cost $17 per hour)
Static budget variable overhead $20000
Static budget fixed overhead $10000
Static budget number of items to produce 30000
Calculate standard predetermined variable overhead, standard predetermined fixed manufacturing overhead, standard cost quality and price for direct materials, standard cost quality and price direct labor.