Question: Disaggregating the Aggregate Plan Use the information below to work the problems in this section. Assume every month has four weeks January demand is 200
Disaggregating the Aggregate Plan
Use the information below to work the problems in this section. Assume every month has four weeks
January demand is 200 February demand is 300
Beginning inventory is 54
Lot size is 150
Firm planned orders for the first six weeks are: 50, 38, 22, 18, 6, and 2 T
he remaining two weeks do not have any firm orders
Develop a master production schedule.