Question: Discharging a contract by executing a new agreement with performance different from what was originally promised is a . a novation. b . a material

Discharging a contract by executing a new agreement with performance different from what was originally promised is
a. a novation.
b. a material breach.
c. substantial performance.
d. an accord and satisfaction.